8440 |
7/24/2024 |
Thomas Alexander |
Laminate flooring to be replaced with new. |
7/24/2024 |
|
|
| |
8441 |
7/24/2024 |
Thomas Alexander |
Laminate flooring to be replaced with new. |
7/24/2024 |
|
|
| |
8319 |
5/6/2024 |
Shibu John |
The body of refrigerator in the basement looks bad because of rust. Need a replacement or fully paint with sprayer. |
5/10/2024 |
|
|
| |
8110 |
12/18/2023 |
Shibu John |
Paint the sides of the current fridge in the basement. |
12/22/2023 |
|
|
| |
8091 |
11/21/2023 |
Thomas Alexander |
Remodel kitchen with new cabinets and counter tops. |
12/4/2023 |
|
|
| |
8080 |
10/26/2023 |
Thomas Alexander |
Generac generator installation, in progress. BGE design for meter and galine upgrade approved and paid. Generator installed and plumbing job completed by 10/2023. Waiting for BGE to install new meter 10/26/2023 |
12/29/2023 |
|
|
| |
8058 |
10/11/2023 |
Shibu John |
2 kitchen cabinets are broken/cracked. Others have wheelchair marks. |