  3345 9/18/2019 Shibu John Roman's Room - Closet door knobs needs to be painted so that both are white. Ref. QA Report 9/18/2019
  3346 9/18/2019 Shibu John BK's Room - Paint the knobs to his closet doors. The paint is peeled off. 9/18/2019
  3347 9/18/2019 Shibu John BK's Room - The Plexiglas on his window needs to be secured/glued on. Its sticking out. Refer QA Report. 9/18/2019
  3348 9/18/2019 Shibu John Living Room - Wall needs to be painted behind the recliner. 9/18/2019
  3349 9/18/2019 Shibu John Main Bathroom - The toilet seat needs to be secured on one side. 9/18/2019
  3350 9/18/2019 Shibu John Main Bathroom - Bath tub needs to be re-glazed. 9/18/2019
  3351 9/18/2019 Shibu John Front Entrance - The ceiling above the door needs to be fixed. Has cracks and stain. 9/18/2019